Case study: optimization of dust binding in a brewery

In a brewery, the dust load in the filtration agitator increased due to the use of xerogels, which led to problems with extraction performance.

As a solution, Bete Germany offered the integration of HA hollow cone nozzles, which produce very fine water droplets to bind dust.

This resulted in optimum dust binding and improved working conditions for the employees. With low acquisition costs and no additional operating costs, the solution proved to be effective and economical.

The brewery benefited from a cleaner environment and less cleaning. The employees were very very satisfied with the improved indoor climate. 